Current projects

After Tangier and Rabat, close-fit lining continues its path through the medinas…

14 December 2022
…and is currently under way in Meknes! At the initiative of His Majesty King Mohammed VI, the Moroccan Government launched a rehabilitation programme in Morocco’s 32 medinas to renew these living and business districts which are home to 750,000 people, i.e., 3.6% of the country’s urban population. At present, 14 of these districts are undergoing active rehabilitation. This programme also enables CTHM to stand out from the competition with the implementation of trenchless techniques which are particularly suited to these dense urban environments, made up of narrow lanes that are home to intense business and retail activity. On behalf of… +

After Tangier and Rabat, close-fit lining continues its path through the medinas…

20 October 2022
…and is currently under way in Rabat! At the initiative of His Majesty King Mohammed VI, the Moroccan Government launched a rehabilitation programme in Morocco’s 32 medinas to renew these living and business districts which are home to 750,000 people, i.e., 3.6% of the country’s urban population. At present, 14 of these districts are undergoing active rehabilitation. This programme also enables CTHM, our Moroccan subsidiary, to stand out from the competition with the implementation of trenchless techniques which are particularly suited to these dense urban environments, made up of narrow lanes that are home to intense business and retail activity.… +

Morocco tops up its order book…

18 May 2021
With a new order for water supply in the north-east of the country! For a project to secure drinking water supply to the city of Oujda, located on the edge of the eastern Rif, ONEE has entrusted our Moroccan subsidiary CTHM with renovation works to leaking water supply pipes leading from the Mechraa Hammadi dam. In 8 months of work, CTHM will execute 3 out of 4 orders, laying more than 45km of networks: Order 1: between the dam and the treatment plant, laying of 13.5km of 1,000mm-diameter PRV and 1km of 1,000mm-diameter steel; Order 2: between the treatment plant… +

CTHM reduces its environmental impact

17 March 2021
CTHM is now lighting its main site using 20 LED projectors powered by a photovoltaic system. In our first episode, both the preparatory work and the routing of the liners were ongoing. The advantages a saving of 32KWH/day, i.e. 972KWH/M of electrical consumption (8 hours of lighting) a reduction of 97.2kg/M in CO2 emissions a significant monthly financial saving no specific connection 8-year projector service life a 1-year economic amortization period… +

Morocco: record lead times on the Targuist and Kharroub worksites

20 January 2021
50km laid in 6 months and 7km in 3 months at the peak of the COVID crisis! And one… SADE Morocco reinforced 50km of ⌀ 300 to 400 PVC drinking water pipes in just 6 months for APDN (Agence pour la Promotion et le Développement du Nord, i.e. agency for the promotion and development of Northern Morocco). The project was costed and won during lockdown despite limited consultation. The aim of this project is to secure the drinking water supply of the town of Targuist from the new desalination plant in the town of Al Hoceima. Located at the heart… +